Lean Planning

We facilitate lean planning meetings on site. Together with the site manager and all subcontractors, we set the planning week by week, so that bottlenecks surface early, commitments are kept and the project suffers fewer delays.

We facilitate planning meetings on site following the lean method. Together with the site manager and all subcontractors, we set the planning week by week: who does what, when, and what needs to be ready before work can start. Bottlenecks surface early, commitments are kept and the project suffers fewer delays.

Phase Planning

We draw up a phase schedule together with all parties involved, working back from the key milestones of the project.

Weekly Planning Meetings

Short weekly meetings with a concrete action list keep everyone aligned and committed to the same planning.

Follow-up of Commitments

We track the agreements made during the meetings and flag bottlenecks early, before they turn into delays.

Visual Planning

A visual planning board on site shows everyone at a glance where the project stands and what comes next.

Continuous Improvement

We look at why planned tasks were not completed and use those lessons to make the following weeks run more smoothly.

Want to start your project?

Learn about all the benefits of a Single Point of Contact Company. We’re here to simplify your project, from A to Z.

Want to start your project?

Learn about all the benefits of a Single Point of Contact Company. We’re here to simplify your project, from A to Z.

Dew and Goldflowers
Projects

Processieweg 44
9450 Haaltert
VAT BE 0845.879.095

Contact info